Import dates
Import timeline planner
With 45 days of production, 5 of inspection, 35 of transit and 10 at destination, an order takes 95 days, and 22 more if Chinese New Year falls inside it. Adjust the days to your case.
Timeline
Pick a date and fill the days with whole numbers.
Factory stoppages considered
| Stoppage | From | To |
|---|---|---|
| Chinese New Year | Feb 10, 2026 | Mar 3, 2026 |
| China National Day | Oct 1, 2026 | Oct 7, 2026 |
| Chinese New Year | Jan 30, 2027 | Feb 20, 2027 |
| China National Day | Oct 1, 2027 | Oct 7, 2027 |
| Chinese New Year | Jan 19, 2028 | Feb 9, 2028 |
| China National Day | Oct 1, 2028 | Oct 7, 2028 |
| Chinese New Year | Feb 6, 2029 | Feb 27, 2029 |
| China National Day | Oct 1, 2029 | Oct 7, 2029 |
Fictional example: an order placed on 5 January 2027
With those days, goods would be ready on 13 March instead of 19 February: Chinese New Year stops production.
Warehouse delivery would be around 2 May 2027.
Common mistakes
- Counting production from the quote instead of the deposit and approved sample.
- Treating Chinese New Year as a one-week holiday.
- Forgetting inspection, space booking and document cut-off.
- Taking port-to-port transit as the delivery date.
Frequently Asked Questions
Quick answers to common questions about this topic
It depends on production and route. Add production, inspection, transit, customs and inland delivery; ask your supplier and forwarder for real figures.
Chinese New Year (about one week before and two after) and the week of 1 October, 2026 to 2029. Other holidays are not included.
Yes. Pick the date you need the goods and you get the latest order date, with no extra buffer.
A calendar file. It opens in Google Calendar, Outlook or your phone calendar and adds each milestone.
Schedule checklist
- Production time is in writing and says when it starts counting.
- Sample and packaging have an approval deadline.
- Inspection is booked before production ends.
- Vessel or air space is booked ahead.
- You checked holidays in China and in your country.
- You left a buffer for delays.
Related guides
More tools
- CBM and container calculatorCubic meters, weight and loading for 20ft, 40ft and 40HC containers.
- Boxes per containerCartons in a 20ft, 40ft or 40HC, with dimensions and max payload.
- Incoterms 2020 selector and comparisonAnswer a few questions and compare who pays each charge and where risk passes.
- FCL or LCL? Break-even pointCompare consolidated and full container with your rates.
- Landed cost estimatorTotal delivered cost: freight, insurance, duties and fees.
- Import payment scheduleHow much to pay and when, by deposit, B/L, arrival or invoice date.
- China credit code validatorCheck the 18-character code of a Chinese supplier.
- Master carton calculatorFrom units to cartons, CBM, weight and MOQ.
- Margin and markup calculatorSelling price by margin on price or markup on cost.
- Import documentsWhat to ask for by transport, product and payment.
- Before you pay your supplierBank account, deposit, balance and warning signs.
Dates are for guidance. Closures vary by factory and China publishes its official calendar late the previous year.